Client: Feni Industry - Kavadarci, R. Македонија Macedonia
Project : Reconstruction of the chain system for transport of raw mine material
Brief Description:
Reconstruction of the chain system for transport of raw mine material
Realized activities:
- Dismantling of chain from Lepol Grid (POLYSIUS) with width 4m, length 90 m and a total weight of 120 tons.; - Dismantling of supporting and return shafts (Total number- 75 ); - Dismantling of driving shaft with bearings; - Dismantling of return shaft with bearings.
Installation of new equipment:
-Assembly of complete driving shaft, with sprockets, housings and bearings ; -Installation of complete return shaft ; -Installation of supporting and return shafts with housings and bearings ; -Installation of new chain width 4 m, length 90 m; -Installation and rehabilitation of other supporting elements; -Alignment and leveling -Putting into operation -Total weight of the dismantled and installed new equipment is cca 180 tons.
|